For better or for worse, I have originated one or two things in the world of construction law in both the UK and Australia. Apart from founding a law firm or two, I was the principal draftsman of the first set of adjudication rules and the first pre-action protocol for construction disputes[3] and coined the terms “pay now, argue later” and Queen of Hearts clause”. I have been making efforts to get pendulum arbitration more widely used to resolve construction disputes.[4]
It was also (and here we get onto the subject matter of this post) me who suggested to John Murray when he was preparing The Murray Report that there should be a statutory benchmark as to which time bars should be enforceable, and which not. It was not exactly suggested as a codification of the existing law, but I pointed out that there are several ways in which a time bar might be challenged, and a single test might be more satisfactory that the existing pot-pourri, referring him to my post ion the topic.
John Murray did pick up that suggestion in his report[5], referring to what I had suggested[6]. The substance of the indicative provision was thus:
(1) A provision in a Construction Contract which purports to make a right to claim or receive payment, or a right to claim or receive an extension of time, conditional upon the provision of any notice shall be of no effect if and insofar as
(a) Compliance with the requirements of the provision would not be reasonably possible or would be unreasonably onerous, or
(b) The requirements of the provision are not reasonably justifiable by any legitimate commercial purpose
(2) For the purpose, “notice” includes any notice, claim for payment, narrative or calculation as to actual or estimated time or money.[7] Continue reading